Dayton Street Utility Improvements

Project Limits

WHAT’S HAPPENING NOW?

Phase 1 of the Dayton Street Utility Improvements Project is wrapping up!

With paving and the majority of the striping on Dayton Street complete between 3rd Ave and 5th Ave, Phase 1 of the Dayton Street Utility Replacement Project is wrapping up! We’d like to thank the community around Dayton Street for their patience during this important project.

Since May 2019, crews have been working to replace the aging and undersized utilities along Dayton Street between 3rd Ave and 5th Ave. Replacing these utilities involved:

    ·   Adding stormwater pipe capacity to reduce flooding downtown during                                      heavy rainstorms
    ·   Replacing and upsizing sewer and potable water pipes that are nearing the                              end of their lifespan
    ·   Repaving and restoring Dayton Street after successful utility replacement.

          Paving overlay on Dayton Street scheduled for Friday, October 11,                                              weather permitting.

Phase 2 construction beginning Early Spring 2020

Phase 2 of the Dayton Street Utility Improvements Project (Dayton Street from 5th Ave S to 9th Ave S) is expected to begin in early March 2020 and last through fall 2020. This work will include:

    ·   Adding stormwater pipe capacity to reduce flooding downtown during                                      heavy rainstorms
    ·   Replacing sewer and potable water pipes that are nearing the end of their                                lifespan
    ·   Repaving the 5th Ave and Dayton Street intersection and concrete                                              crosswalks
    ·   Upgrading curb ramps to be ADA-accessible at the intersections of Dayton                                Street and 6th, 7th, 8th, and 9th Avenues
    ·   Adding a sidewalk along the south side of Dayton Street from 7th Ave to 8th                            Ave, where there currently is no sidewalk.

In preparation for Phase 2, limited low-impact work will occur on Dayton between 7th and 9th  as soon as late November 2019 to aid and prepare the site  for the next phase of construction. We will follow up with more information as this work is scheduled.

Community Transit buses will be running on alternate routes around work zones. Please visit Community Transit’s website for current rider alerts and routes: https://www.communitytransit.org/alert

Stay Informed on Project Updates

arrow b  Please stay tuned to this website for regular updates. We will be sharing project updates via email. To sign up for regular updates, or if you have questions or comments, email us at daytonproject@edmondswa.gov

arrow b  Check out our live feed of the construction site at: https://www.senserasystems.com/public/project/DaytonStProjec

arrow b  You can also follow project progress on Twitter at @DaytonStProject. 

Phase 1 (May-October 2019) and Phase 2 (2020)

Phase 1 of construction (Dayton Street from 3rd Ave S to 5th Ave S) will begin on May 13, 2019 and is anticipated to be completed in Fall 2019. Work during this phase will occur mostly between 3rd Ave S and 5th Ave S. Some sewer pipe rehabilitation work between 6th and 9th may be part of phase 1.

Traffic and pedestrian impacts

arrow b   One lane of traffic, either eastbound or westbound, will be maintained on Dayton St during most of construction.  Traffic control will be present ot direct people through the work area during construction.

arrow b   Parking will be restricted in the work area

arrow b   To provide safe working spaces for construction crews, there may be temporary intersection and/or block closures lasting for 1 to 3 days. We will notify businesses and neighbors ahead of these closures

arrow b   Sidewalks and driveways will remain open except for short durations to maintain safety throughout the corridor

 
Phase 2 of construction  (Dayton Street from 5th Ave S to 9th Ave S) will begin as early as Spring 2020 and last into Fall 2020

Project Description:

The Dayton Street Utility Improvements Project will replace aging and undersized utilities along Dayton Street from 3rd Ave S to 9th Ave S. Improvements will include:
    • Adding stormwater pipe capacity to reduce flooding in downtown during heavy rainstorms

    • Replacing sewer and potable water pipes that are nearing the end of their lifespan

    • Upgrading curb ramps to be ADA-accessible at the intersections of Dayton Street and 6th, 7th, 8th, and 9th Avenues

    • Adding a sidewalk along the south side of Dayton Street from 7th to 8th Avenues

Estimated Schedule:

  • Design was completed at the end of 2018

  • Phase 1 (3rd Ave S to 5th Ave S) construction will begin in May 2019

  • Crews do not plan to work between October 2019 and March 2020 over the holiday season

  • Construction will be divided into two phases. The second phase of construction (5th Ave S to 9th Ave S) is expected to start as early as Spring 2020 and last into Fall 2020

Scope:

Replace and upsize existing utilities on Dayton Street from 3rd to 9th Avenue. Improvements will include:

  • Replacing 3200 feet of stormwater pipe

  • Replacing 3800 feet of potable water pipe

  • Replacing 4300 feet of sanitary sewer pipe

  • New pavement on Dayton Street throughout the project limits

  • Constructing a new sidewalk on the south side of Dayton between 7th 
    and 8th Avenues

  • Constructing ADA-accessible pedestrian curb ramps

  • Revise sidewalks and intersections at Dayton St and 6th, 7th, and 8th, and 9th Avenues

Cost:

 ·  Construction costs estimated to be $7 million.

Utility Section Near 5th & Dayton

Cover

CLICK IMAGE TO ENLARGE

Schematic Utility Replacement Design

Dayton scroll plot

Dayton Street Project Contact

Construction Management Team
daytonproject@edmondswa.gov
425-771-0220

Follow us on Twitter at:
https://twitter.com/DaytonStProject

Check out our live stream at:
View Livestream

Public Works Engineering Division
City Hall - Second Floor
121 5th Ave N
Edmonds, WA 98020

Phone: (425) 771-0220
Fax: (425) 672-5750
engineering@edmondswa.gov

Public Hours:
8:00am to 4:30pm - M, T, Th, F
Wed 8:30am to Noon

Closed Weekends and Holidays

Engineering Capital Project Staff
Engineering Development Staff